Variations guide topic
Variation not paid: why extra work goes unpaid
“Just crack on, we’ll sort the money later.” Weeks on, the extra work is built in, the instruction cannot be found and the final account does not include it.
What a variation is
A variation is a change to what you were originally contracted to do: more work, less work or different work. Most jobs have them, and most contracts say how they should be instructed and paid for.
Why extras go unpaid
- The instruction was verbal and nobody confirmed it.
- The person who gave it had no authority under the contract.
- There was a time limit for notifying the change and it was missed.
- Nobody agreed the price before the work began.
- The records are too thin to show what happened.
A verbal instruction is not necessarily invalid
A verbal instruction can still be a valid instruction. The real risk is proof. Without a record, it is your word against theirs weeks or months later.
Why timing matters
Many contracts, including common JCT and NEC forms, set rules and time limits on notifying changes. Missing one can put an otherwise fair claim at risk, so the contract is the first thing to read.
Where the detail is
The Variations guide covers what counts as a variation, who can instruct you, verbal instructions, notices and time limits, valuation, records, and getting variations into applications and the final account. It includes a worked example and templates, including a confirmation of a verbal instruction.
Common questions
Do I have to stop work until a variation is agreed?
Not necessarily. It depends on the contract and the situation. The key risk is having no record of what was agreed, so take advice if the sums are large.
Is a variation the same as a compensation event?
They do similar jobs under different contracts. A compensation event is the NEC term, and its rules and time limits are different from JCT.