Pay when paid clauses in UK construction: are they legal?
“We will pay you when the client pays us.” It is one of the oldest lines in subcontracting, and it is often put in a contract as if it were the end of the conversation.
What a pay when paid clause is
A clause that makes your payment depend on the payer being paid by someone else further up the chain. If they have not been paid, the clause says, neither will you.
What the Construction Act says
For most construction contracts, the Act makes pay when paid clauses ineffective. There is a limited exception where someone further up the chain is insolvent.
A related rule restricts “pay when certified” style conditions, where payment depends on something happening under another contract. The detail of how far that goes is worth checking against your own wording.
Why it still matters
A clause that is ineffective can still scare someone into waiting. Plenty of subcontractors accept “the client hasn’t paid us” as a reason, when it may not be one.
It also shows up in retention release. “We release yours when the client releases ours” is a common excuse.
Scope
The Act’s payment rules generally apply to construction contracts in England and Wales, including some part-written or verbal ones, and generally not to work for a homeowner on the home they live in. Scotland and Northern Ireland have their own versions.
Where the detail is
The Contracts guide covers what the Construction Act puts into your contract, payment terms to check first, and how to spot payment conditions that should worry you before you sign. The Retention guide covers it in the context of release.
Common questions
Does this mean the payer must always pay on time?
No. It means they cannot generally use this kind of clause as a reason not to. Other payment rules still apply.
Can I just cross the clause out?
Do not change a contract without agreement. Raise it before you sign.